Requisitions created after PO's???
答案:2 悬赏:60 手机版
解决时间 2021-01-26 05:27
- 提问者网友:夢醒日落
- 2021-01-25 14:12
Requisitions created after PO's???
最佳答案
- 五星知识达人网友:大漠
- 2021-01-25 15:16
I would not go for this option unless you are chosing external numbering range for your PO Document Type. If the internal number range has been defined for your PO Document Type in configuration, then it is impossible for you to make any 'advance reservation' for your Emergency PO transactions. Besides, I don't really see the actual linkage between the approval consistency, the PR release strategy and the emergency transactions. If you have set up the PR release strategy, then it should be applicable for both normal and emergency PRs and both types of PRs can be well converted into PO without any problem.Cheers,HT
全部回答
- 1楼网友:不如潦草
- 2021-01-25 16:26
If you are on 4.6x and above, then you can just go to the Item Details delivery schedule tab and add the requisition to an existing line item (if its the same material) or to a new line item.
我要举报
如以上问答信息为低俗、色情、不良、暴力、侵权、涉及违法等信息,可以点下面链接进行举报!
大家都在看
推荐资讯